Telecommunication Infrastructure Upgrade Project

   
Construction Dates

April 2008 to May 2009

Description

This project will construct new intermediate data centers (IDC’s), provide dedicated raceways in the form of cable trays, and provide new data outlets.  This project will bring fiber and enhanced CAT-6 copper cable to desktops.

Progress Report
  • Construction of IDC rooms in HSS, Thornton Hall, Creative Arts, Fine Arts, Administration building and Science building is under way and is scheduled to be finished in June 2008.
  • Fire-stopping of wall penetrations at Burk Hall and Business building is near completion pending inspection by the Fire Marshal.
  • Installation of telecommunication conveyance system in Gymnasium is under construction and is scheduled to be finished in June 2008.The inter-building telecommunication project will connect all campus buildings to the computer center in old Administration building, work for this project is planned to start in June 2008, and is scheduled to be finished in August 2008.The Administration building ceiling replacement and cable tray installation is planned to start in June 2008, and is scheduled to be finished in August 2008.
  • The intra-building telecommunication project will complete the installation of telecommunication conveyance system, wiring, and outlets in HSS, Science building, Gymnasium, Fine Arts, Creative Arts, Administration building, and Thornton Hall. This project is scheduled to start in July 2008, and scheduled to be finished in May 2009.

 

   
   

 