Construction Dates
June 1, 2009 – August 7, 2009
Description

As part of the overall renovations of Mary Park and Mary Ward Halls this summer, the interiors of the residence halls are being painted.

Scope of work

The painting scope of work includes all student rooms, corridors, lobbies, lounges, door frames and doors, offices, and laundry rooms. An overall color scheme was chosen with distinct finishes for walls, ceilings and trim.

Progress Report

As of late June, the painting contractor is on schedule and has almost completed four floors at Mary Park Hall and has a crew working in Mary Ward Hall, as well.