University Park North Seismic Upgrade
Construction Dates |
May 2007 to late summer 2008 |
Description |
This project includes the voluntary seismic strengthening of four (4) ten story occupied apartment buildings on the grounds of San Francisco State University. The work will be executed in two phases of two buildings each. |
Scope of work |
This project includes the voluntary seismic strengthening of four (4) ten story occupied apartment buildings on the grounds of San Francisco State University. The work will be executed in two phases of two buildings each. Generally, the work will include the following scope:
|
Progress Report |
Work is now underway sandblasting the exteriors of 285/295 and 325/335 Buckingham Way to remove paint and prepare the surfaces for the thickening of concrete shear walls. This work is currently being performed on enclosed scaffolds in the central courtyards of the buildings, will eventually move to the ends of the buildings, and is extremely noisy. In addition, interior work is continuing in Buildings 8 and 9 to make 5 units in each building accessible, as well as preparation for the installation of steel tie rods on the second and third floors.
In March 2008, finishing and painting of the exterior shear walls for Phase I was completed. The DYWIDAG rods were de-tensioned to allow repair of the cracks in the ‘dead-ends,’ a uniform bearing surface was constructed and the rods were re-tensioned. Work on the interior units to be made accessible continued. Scaffolding is being erected on the Phase II buildings and sandblasting has started on the ends of the buildings. |
Details |
Construction will involve two phases: |