University Housing Telecommunication Upgrade

   
Construction Dates
Spring 2008 to Spring 2010 (completed)
Description

The project provides every housing unit on campus with a consistent telecommunications package including satellite television, high-speed internet and VoIP telephone service. The project is phased as follows: Phase 1: core campus housing; Phase 2: UPS; and Phase 3: UPN.

Scope of work

The first phase of the project involves the upgrade of network cabling and connection in Mary Park and Mary Ward Halls, as well as the construction of a satellite television head-end in the basement of the Village at Centennial Square.

 

   
   

 