Children’s Campus at SF State
Construction Dates |
December 2007 to January 2009 (completed) |
Description |
This project provides a temporary child development facility for the Marian Wright Edelman Institute in a modular building on the site of the former Lakeview Center building. |
Scope of work |
|
Progress Report |
The Children's Campus on North State Drive is under construction. On November 23rd through 25, twenty two factory built building modules will be delivered and installed on the newly completed foundation walls to create a one story facility of approximately 8000 square feet. On the 23rd and 24th there could be some temporary blocking of part of North State Drive while the modles are moved into position to be off loaded by a crane. |
Details |
Winston Drive stairwase is now open. |