Student Health Center -- Pharmacy Shelving Upgrade

   
Construction Dates

July 2008

Description

This project will replace the shelving in the Student Health Center’s Pharmacy to provide a more efficient work flow and will incorporate new dispensing equipment into this area.

Scope of work

Work involves removal of existing shelving and perimeter casework and installation of new storage units and fixtures.  In addition, new carpet will be installed, walls will be painted and electrical service within the Pharmacy will be expanded.

 

Progress Report

Shop drawings have been reviewed and new fixtures are currently being fabricated.  On-site work is scheduled to commence on July 24, 2008.

 